Development Plan
The Company’s re-opening plan (“Development Plan”) is based on utilizing existing infrastructure as much as possible.
The new milling facility would be located a short distance from the Super Pit and uphill from the existing tailing management facility. The new mill facility, pit shovels and drills will receive power via a short power line extension from the existing 138 kv power line. Ore from the Super Pit will be trucked using 11 240 ton haul trucks. The project mineral tenure area totals 6700 hectares, of which 875 hectares (13%) has been historically developed, while 225 hectares (3.4%) will be new development to accommodate the expanded facilities.